Skip to main content

River Flows for Hydro Plants

You may track, on an hourly basis, water levels and flows of the recreational rivers and lakes near AEP's hydroelectric facilities. See a map of our plant locations.

Explanation of Terms

  • The "Forebay" and "Tailwater" numbers show the feet above sea level of the water levels immediately upstream and downstream from our plants.
  • "Tailwater Flow" is the hourly average of the river flow just downstream of the plants, measured in cubic feet per second.

New River Flows & Forecasts

Water release information for AEP's Claytor, Buck, and Byllesby hydro dams is updated every fifteen minutes. Forecast information is estimated. Water travel times may be affected by water conditions, precipitation in the watershed and other factors.

Most Recent Conditions

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Buck2003.402002.931960.381232
Byllesby2079.202078.752020.871270
Claytor1846.001845.731730.741937
See plant-specific notices below. Data last updated on Aug 24 2025, 2:49 AM EST. Tail water (cfs) is last hour average.

Downstream Forecasts

Forecast information shows water release information from the Claytor Dam, delayed to account for the average time it takes the released water to reach particular points downstream. Water travel times may be affected by water conditions, precipitation in the watershed and other factors.

Kanawha River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
London614.00614.02590.682321
Marmet590.00590.01566.373271
Winfield566.00566.38538.750
See plant-specific notices below. Data last updated on Aug 24 2025, 2:49 AM EST. Tail water (cfs) is last hour average.

Roanoke River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Niagara885.00884.89
Smith Mountain795.00793.96604.06
Leesville613.00.00607.00532.09718
See plant-specific notices below. Data last updated on Aug 24 2025, 2:49 AM EST. Tail water (cfs) is last hour average.

Saint Joseph River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Constantine782.90782.92771.13
MottvilleSummer: 770.40
Winter: 770.00
770.41758.17724
Elkhart741.50
winter: 739.50
741.55721.60
Twin Branch717.10716.89696.051211
BuchananSummer: 637.50
Winter: 637.00
637.47624.201243
Berrien Springs623.50623.54598.191779
See plant-specific notices below. Data last updated on Aug 24 2025, 2:49 AM EST. Tail water (cfs) is last hour average.

Plant–Specific Notices

As of 05:00 this morning, Saturday August 23, 2025, inflow to the Smith Mountain Project is 1260 CFS and the discharge from Leesville is 1026 CFS. The adjusted reservoir elevation is 794.9 ft. The flow rate at the USGS Gauge at Brookneal was 1120 CFS, Stage 4.78 ft. and at Altavista 1120 CFS, Stage 2.52 ft.